20/20 Communications posts new updates to the Wireless Washtenaw section of our site every Wednesday afternoon. Wireless Washtenaw updates are also available through our RSS Feed and Mailing List.
|
| November 22 , 2007 |
|
 |
| Siemens continues to perform acceptance testing for the: |
 |
|
|
| |
| November 15, 2007 |
|
 |
| On Friday, November 10th, 20/20 Communications received the prestigious Ann Arbor Business Review's Technology category, "Deal of the Year" award for obtaining the Wireless Washtenaw Bid. For the full article, pick up the November 16th edition of the Business Review. |
 |
|
|
| |
| November 8, 2007 |
|
 |
| We are continuing to install radios in the Ann Arbor, Saline and Manchester Pilot areas. All radio installations are scheduled for completion on Friday November 10. Acceptance and performance testing will begin on November 13th and run through the end of the month. |
 |
|
|
| |
| November 1, 2007 |
|
 |
| This week, we began installing and configuring the Wireless Integration Platform and the first of the pilot's 40 radios. |
 |
|
|
| |
|
|
|
|
|
|
|