| Updates - Page 6 of 7 |
|
| |
20/20 Communications posts new updates to the Wireless Washtenaw section of our site every Wednesday afternoon. Wireless Washtenaw updates are also available through our RSS Feed and Mailing List.
|
| |
| December 27 , 2007 |
|
 |
| The response to last Wednesday's Ann Arbor News article, the information line update, the weekly website update and the $7.95 dial-up offer for UofM faculty and staff has been positively overwhelming. We (meaning Katie Barker and myself) are in the process of returning over 120 voicemails |
 |
|
|
| |
| December 20, 2007 |
|
 |
| The Wireless Washtenaw project now has 25 pilot participants located throughout the Manchester, Saline and Ann Arbor pilot areas. Residents throughout the county are contacting us by phone and email requesting |
 |
|
|
| |
| December 13 , 2007 |
|
 |
| 20/20 Communications began activating pilot participants in the Manchester and Saline areas on Friday, December 8th. The average installation time in the rural areas is between 1 to 1.5 hours. Shorter installation periods are anticipated as the 20/20 staff becomes more familiar with the installation of the new BelAir equipment. |
 |
|
|
| |
| December 6 , 2007 |
|
 |
| Siemens engineers completed acceptance testing for the pilot areas as scheduled on Thursday, November 30. December 1st was their last day on site. |
 |
|
|
| |
| November 29 , 2007 |
|
 |
| Siemens engineers are wrapping up acceptance testing for the pilot areas. This testing is scheduled for completion on Thursday, November 30th, 2006. |
 |
|
|
| |
|
|
|
|
|
|
|